After migration to Project Server 2013, I have found several bugs that have been confirmed but not yet resolved by Microsoft.
One of them:
For
timesheets in approval center, while applying "Resources" filter and fetching
timesheets with "Resource Name", project server 2013 does not show any
timesheets
As of October 2013,
RESOLUTION:- Resource filter issue in 2013 is reproducible with latest CU in-house.
- This looks to be a known bug in project server 2013 and we have already filed an internal bug.
- But, as an alternate solution, you can uncheck both "Date" and "Resource" filters and then use resource name to get the timesheet.