‘Lost Resources’ bug has came back after re-relased SP1 for PS2013 has been applied.
To fix it - you need to manually re-add the missing resources in the project.
Plus, you need to run the SQL to fix 2 PS procedures, as it was recommended in http://support.microsoft.com/kb/2933444
draft.MSP_WINPROJ_DELETE_OLD_PROJECT_RESOURCESpub.MSP_WINPROJ_DELETE_OLD_PROJECT_RESOURCES
I have run the sql before SP1, then I have applied SP1 and compare procedures before and after:
1. [draft].[MSP_WINPROJ_DELETE_OLD_PROJECT_RESOURCES]
The procedure was re-created by SP1 (the service packed was installed on 5/21/2014)
and the SQL delete statement lacks filter by PROJ_UID
WHERE RES_UID IN (SELECT RES_UID FROM @resUids)
2. [pub].[MSP_WINPROJ_DELETE_OLD_PROJECT_RESOURCES]
The procedure was re-created by SP1 (the service packed was installed on 5/21/2014)
and the SQL delete statement lacks filter by PROJ_UID
and the SQL delete statement lacks filter by PROJ_UID
WHERE RES_UID IN (SELECT RES_UID FROM @resUids)